- VARIATIONS
- Definitions
- The following terms shall have the following meanings:
- "Direct Cost" has the meaning given in Appendix A of this Schedule 22.
- "Estimate" has the meaning given in Section 1.4(a) of this Schedule 22.
- "HMQ Work" has the meaning given in Section 1.7(a) of this Schedule 22.
- "Project Co Variation Notice" has the meaning given in Section 2.1(a) of this Schedule 22.
- "Variation" means a variation, addition, reduction, substitution, omission, modification, deletion, removal or other change to the whole or any part of the Project Operations, including in relation to the whole or any part of the Works or the OM&R Work.
- "Variation Confirmation" has the meaning given in Section 1.8(a)(ii) of this Schedule 22.
- "Variation Directive" means a written instruction which is issued on a form designated as a "Variation Directive Form" and signed by the HMQ Representative directing Project Co to immediately proceed with a Variation pending the finalization and issuance of a Variation Confirmation for that Variation.
- "Variation Enquiry" has the meaning given in Section 1.3(a) of this Schedule 22.
- General
- HMQ has the right from time to time to propose and require Project Co to carry out and implement a Variation, and any such Variation shall be subject to the provisions of this Schedule 22, provided that HMQ shall not be permitted to withdraw a Variation Enquiry (nor will a Variation Enquiry be deemed to have been withdrawn) with respect to those circumstances specified in the Project Agreement for which HMQ is obligated to proceed with a Variation.
- HMQ shall be obligated to proceed with a Variation in certain circumstances specified in this Project Agreement, and any such Variation shall be subject to the provisions of this Schedule 22.
- Project Co will not be entitled to any payment, compensation or extension of time for a Variation except to the extent provided in a Variation Confirmation or Variation Directive in accordance with this Schedule 22.
- Variation Enquiry
- If HMQ proposes or is obligated pursuant to the terms of this Project Agreement or Applicable Law to initiate a Variation it shall deliver to Project Co a written notice of the proposed Variation (a "Variation Enquiry").
- A Variation Enquiry shall:
- describe the proposed Variation with sufficient detail to enable Project Co to prepare a detailed Estimate;
- in the event that the proposed Variation will require a Capital Expenditure, state whether HMQ intends to pay for the Variation by way of lump sum payment or payments, adjustment to the Monthly OM&R Payments (and, if applicable, with a request for Project Co to obtain financing for all or part of the Variation), or a combination thereof; and
- provide a preliminary indication of any provisions of this Project Agreement (including the Output Specifications or the Project Co Proposal Extracts) that will be affected by the proposed Variation, as well as the amendments to this Project Agreement (including the Output Specifications or the Project Co Proposal Extracts) that may be necessary to accommodate the Variation.
- Delivery of Estimate
- As soon as practicable and in any event within 15 Business Days after receipt of a Variation Enquiry, or such longer period as the Parties agree acting reasonably, Project Co shall deliver its detailed breakdown, estimate and other information (an "Estimate") prepared in accordance with and meeting the requirements of Section 1.6.
- Project Co Grounds for Objection
- Project Co may only refuse to deliver an Estimate if Project Co can demonstrate to HMQ's satisfaction, acting reasonably, within the period for delivery of an Estimate specified or agreed pursuant to Section 1.4(a), that:
- the implementation of the Variation would materially and adversely affect the health and safety of any person;
- the implementation of the Variation would:
- infringe Applicable Law;
- cause to be revoked any of the existing Permits, Licences or Approvals required by Project Co to perform the Project Operations, and any such Permit, Licence or Approval is not, using commercially reasonable efforts, capable of amendment or renewal; or
- require any new Permits, Licences or Approvals for Project Co to perform the Project Operations, any of which will not, using commercially reasonable efforts by Project Co or HMQ, as applicable, be obtainable;
- the proposed Variation would have a material and adverse effect on performance of the Project Operations (except those Project Operations which have been specified as requiring amendment in the Variation Enquiry) in a manner not compensated pursuant to this Schedule 22;
- the implementation of the Variation would be a departure from Good Industry Practice;
- HMQ does not have the legal power or capacity to require the Variation to be implemented or to do anything envisaged by this Schedule 22 in respect of or in connection with the Variation;
- the Variation would, if implemented, result in a change in the essential nature of the Parkway;
- the Variation Enquiry does not comply with the requirements of Section 1.3 (including a failure to include adequate information therein to enable Project Co to prepare an Estimate in respect thereof);
- in the case of a Variation relating to the Works, the time specified for commencement and/or completion of such Variation cannot be achieved by Project Co despite commercially reasonable efforts; or
- in the case of a Variation relating to the OM&R Work, the time specified for implementation of such Variation cannot be achieved by Project Co despite commercially reasonable efforts.
- If Project Co refuses to provide an Estimate on the grounds set out in Section 1.5(a), Project Co shall, within the period for delivery of an Estimate specified or agreed pursuant to Section 1.4(a), deliver to HMQ a written notice specifying the grounds upon which Project Co rejects the Variation and the details thereof.
- Estimate Requirements
- HMQ's Right to Perform
- In respect of Phase One or Phase Two, after the respective Phase Substantial Completion and in respect of the entire Parkway, after Substantial Completion, HMQ shall have the right to perform the subject matter of a proposed Variation ("HMQ Work") itself, or through others contracting directly with HMQ, without compensation to Project Co, except as specifically stated herein.
- HMQ shall indemnify and save Project Co harmless from and against any and all loss or expense which may be suffered, sustained or incurred by Project Co as a direct result of, in respect of, or arising out of the performance by HMQ, or any third party, of HMQ Work, including, without limitation, any loss or expense related to any adverse impacts on the Project Operations.
- Variation Confirmation
- Financing
- If Project Co in its Estimate confirms that existing financing is not available to pay for the proposed Variation and if HMQ requests Project Co to obtain financing for a Variation, then a Variation Confirmation may be issued subject to Project Co obtaining financing. In such event, Project Co shall use commercially reasonable efforts to obtain the requested financing on terms satisfactory to Project Co, the Lenders and HMQ, provided that, prior to the Substantial Completion Date, Project Co shall not be required to seek financing from any source other than the Lenders.
- If Project Co has used commercially reasonable efforts to obtain the requested financing but has been unable to obtain an offer of financing on terms reasonably satisfactory to Project Co and HMQ within 60 days of the date that HMQ issues the Variation Confirmation, then Project Co shall have no further obligation to obtain financing for the Variation and any Variation Confirmation subject to financing shall no longer have any effect unless HMQ, in its sole discretion, waives the requirement for financing or unless HMQ is obligated to proceed with the Variation pursuant to the terms of this Project Agreement.
- If Project Co obtains an offer of financing on terms reasonably satisfactory to Project Co, Project Co shall provide HMQ with details of such financing, and HMQ shall, in its sole discretion, determine whether Project Co should proceed with such financing. If HMQ determines that Project Co should not proceed with such financing, then Project Co shall have no further obligation to obtain financing for the Variation and any Variation Confirmation subject to financing shall no longer have any effect unless HMQ, in its sole discretion, waives the requirement for financing or unless HMQ is obligated to proceed with the Variation pursuant to the terms of this Project Agreement.
- HMQ may at any time withdraw the requirement for Project Co to use commercially reasonable efforts to obtain financing, after which Project Co shall have no further obligation to obtain financing for the Variation and any Variation Confirmation subject to financing shall no longer have any effect unless HMQ in its sole discretion waives the requirement for financing or unless HMQ is obligated to proceed with the Variation pursuant to the terms of this Project Agreement.
- If HMQ waives the requirement for financing or if Project Co has no further obligation to obtain financing for the Variation pursuant to Sections 1.9(b), 1.9(c) or 1.9(d), then Project Co shall proceed with the Variation as set out in the Variation Confirmation and HMQ shall pay for the Variation as provided for in Section 1.10(a)(ii).
- Payment
- If a Variation Confirmation has been issued and is not subject to financing, or if the requirement for financing has been satisfied by Project Co or has been waived by HMQ, a price adjustment for the Variation, as set out in the Estimate and as adjusted and confirmed by the Variation Confirmation, shall be made as follows:
- the Monthly OM&R Payments shall be adjusted as set out in the Variation Confirmation; and
- payment for Capital Expenditures as set out in the Variation Confirmation and not financed by Project Co shall be paid as follows:
- HMQ shall pay such Capital Expenditures in lump sum payments based on a payment schedule agreed by HMQ and Project Co, acting reasonably, to reflect the amount and timing of the Capital Expenditures to be incurred by Project Co in carrying out the Variation to the extent borne by HMQ; and
- where payment for part of the Variation reflects the carrying out of, or specific progress towards, an element within the Variation, Project Co shall provide satisfactory evidence confirming that the part of the Variation corresponding to each occasion when payment is due under the payment schedule has been duly carried out.
In the event HMQ and Project Co fail to agree as to the terms of the payment schedule, the payment schedule shall be determined in accordance with Schedule 27 - Dispute Resolution Procedure, provided that, where all or any part of the Variation is being carried out by a third party under a contract with Project Co, subject to the terms of any contract between Project Co and that third party in relation to the implementation of the Variation having been approved by HMQ (such approval not to be unreasonably withheld or delayed), the process under Schedule 27 - Dispute Resolution Procedure shall determine a payment schedule which would enable Project Co to be funded by HMQ in time to make payments to that third party in accordance with its contract with Project Co.
- HMQ shall make payment to Project Co within 20 Business Days of receipt by HMQ of invoices presented to HMQ in accordance with the agreed payment schedule accompanied (where applicable) by the relevant evidence that the relevant part of the Variation has been carried out.
- Payments by HMQ in respect of a Variation shall be subject to applicable holdback provisions of the Construction Lien Act (Ontario), as applicable.
- Project Co shall not be entitled to any amount in excess of the amount of the Estimate confirmed in the Variation Confirmation.
- Upon request by Project Co, HMQ shall provide to Project Co copies of any consent or approval issued by HMQ in connection with a proposed Variation.
- Reduction in Project Operations
- If a Variation involves any reduction in Project Operations which results in savings in Direct Costs to Project Co, such savings shall result in a reduction in the compensation payable to Project Co under this Project Agreement in an amount equal to such reduction in Direct Costs, and Project Co shall compensate HMQ by way of a reduction in the Monthly OM&R Payments.
- Variation Directive
- If an Estimate is not promptly agreed upon by HMQ and Project Co or if there is a Dispute in relation thereto or if HMQ, in its sole discretion, requires a Variation to be implemented prior to issuing a Variation Confirmation, then HMQ may issue a Variation Directive and, following receipt of the Variation Directive:
- Project Co shall promptly proceed with the Variation;
- the determination of the valuation and time extensions, if any, required in connection with such Variation, shall be made as soon as reasonably possible after commencement of the implementation of the Variation; and
- pending final determination of the valuation and time extensions, if any, required in connection with such Variation, the Independent Certifier (if such Variation is in respect of matters prior to Final Completion) or the HMQ Representative, as applicable and, in each case, acting reasonably, shall determine the valuation in accordance with Appendices A and B hereto, with any Dispute to be determined in accordance with Schedule 27 - Dispute Resolution Procedure,
provided that, HMQ shall fund all Variations implemented by way of a Variation Directive as provided for in Section 1.10(a)(ii).
- PROJECT CO VARIATIONS
- General
- Project Co shall deliver to HMQ a written notice (a "Project Co Variation Notice") for each Variation proposed by Project Co.
- Project Co Variation Notice
- A Project Co Variation Notice shall:
- set out details of the proposed Variation in sufficient detail to enable HMQ to evaluate it in full;
- specify Project Co's reasons for proposing the Variation;
- indicate all reasonably foreseeable implications of the Variation, including whether there are any costs or cost savings to HMQ, and whether an adjustment to the Monthly OM&R Payments is required; and
- indicate the latest date by which a Variation Enquiry must be issued.
- If HMQ, in its sole discretion, elects to consider the Variation proposed by Project Co, HMQ may issue to Project Co a Variation Enquiry and the procedure set out in Section 1 will apply.
- SMALL WORKS
- General
- After the relevant Phase Substantial Completion Date with respect to Phase One and Phase Two and after the Substantial Completion Date with respect to the entire Parkway, Project Co shall carry out all Small Works requested by HMQ.
- If Small Works are requested by HMQ, Project Co shall, within 10 Business Days of each such request and prior to carrying out the Small Works, provide HMQ with a price for carrying out the Small Works.
- If Project Co's price is accepted by HMQ, in its sole discretion, Project Co shall carry out the Small Works for such price.
- HMQ may at any time, in its sole discretion, including if HMQ does not accept the price proposed by Project Co pursuant to Section 3.1(b), issue a Variation Enquiry or Variation Directive in respect of such Small Works, in which event the provisions of this Schedule 22, other than this Section 3, shall apply.
- Project Co's price shall include only its Direct Costs, as calculated in accordance with Appendix A, together with applicable margins as set out in Appendix B.
- Project Co to Minimize Inconvenience
- Project Co shall notify HMQ of the estimated duration of any Small Works so that HMQ and Project Co can agree upon a convenient time for carrying out the same, so as to minimize and mitigate inconvenience and disruption to HMQ. Project Co shall use commercially reasonable efforts to minimize the duration of any Small Works.
APPENDIX A
CALCULATION OF DIRECT COSTS
- DIRECT COSTS
- Subject to Section 1.2 of this Appendix A, the term "Direct Cost" means the cumulative total, without duplication, of only the following amounts, as paid or incurred by Project Co or each Subcontractor, as applicable, to the extent that they specifically relate to, and are attributable to, the Variation under which Project Co is expressly entitled to its Direct Cost and would not otherwise have been incurred:
- wages and benefits paid for labour in the direct employ of Project Co or each Subcontractor while performing that part of the Project Operations on the Site;
- salaries, wages and benefits of Project Co's or each Subcontractor's personnel when stationed at the Site office in whatever capacity employed, or personnel engaged at shops or on the road, in expediting the production or transportation of materials or equipment;
- salaries, wages and benefits of Project Co's or each Subcontractor's office personnel engaged in a technical capacity;
- without limiting Sections 1.1(i), 1.1(ii) and 1.1(iii) of this Appendix A, contributions, assessments or taxes incurred for such items as employment insurance, provincial health insurance, workers' compensation, and Canada Pension Plan, insofar as such costs are based on the wages, salaries, or other remuneration paid to Project Co for employees pursuant to Sections 1.1(i), 1.1(ii) and 1.1(iii) of this Appendix A, but excluding for certainty all income taxes on such wages, salaries and other remuneration;
- travel and subsistence expenses of Project Co's or each Subcontractor's officers or employees referred to in Sections 1.1(i), 1.1(ii) and 1.1(iii) of this Appendix A;
- the cost of materials (including hand tools which have a retail value of $[REDACTED] or less), products, supplies, equipment, temporary services and facilities, including transportation and maintenance thereof, which are consumed in the performance of the Variation;
- the rental costs of all tools (excluding hand tools which have a retail value of $[REDACTED] or less), machinery, and equipment used in the performance of the Variation, whether rented from or provided by Project Co or others, including installation, minor repair and replacement, dismantling, removal, transportation and delivery costs thereof;
- deposits lost;
- the amount of all Subcontracts with Subcontractors;
- the amount paid for any design services;
- the cost of third party quality assurance required by HMQ, such as independent inspection and testing services;
- charges levied by Governmental Authorities, but excluding fines or penalties not related to the implementation of the Variation;
- subject to Section 1.1(iv) of this Appendix A, Taxes (and without limiting the obligation of HMQ to pay HST payable by it under this Project Agreement), but excluding:
- HST;
- taxes imposed on Project Co or a Subcontractor based on or measured by income or profit or otherwise imposed under the Income Tax Act (Canada), the Income Tax Act (Ontario) or any similar statute in any other jurisdiction;
- capital taxes based on or measured by the capital of Project Co or a Subcontractor;
- taxes relating to withholdings on any payments by Project Co or a Subcontractor; and
- taxes relating to any business or activity other than the business or activities related to, and conducted for, the purposes of the Project Operations;
- the cost of removal and disposal of contaminants, hazardous substances, waste products and debris for which Project Co is not responsible under this Project Agreement;
- termination payments which are required under Applicable Law to be made to employees of Project Co reasonably and properly incurred by Project Co arising as a direct result of any Variation reducing the scope of the Project Operations, except to the extent that such termination payments are provided for in contracts of employment, agreements or arrangements that were not entered into in the ordinary course of business and on commercial arm's length terms;
- the cost of financing, including additional financing costs related to any delay caused by the implementation of the Variation;
- the cost of competitively tendering any contract in relation to the proposed Variation which is required by Applicable Law or any policy applicable to HMQ;
- the cost of any additional insurance or performance security required or approved by HMQ;
- the cost of obtaining all Project Co Permits, Licences and Approvals; and
- reasonable fees and disbursements of Project Co's legal advisors.
- The Direct Cost otherwise payable shall be subject to and limited by the following:
- the Direct Cost shall be net of all discounts, rebates and other price reductions and benefits, which relate to the Direct Cost incurred;
- the amount paid for materials, products, supplies and equipment incorporated into the Project Operations as a result of the Variation shall not exceed commercially competitive rates available in the Province of Ontario for such materials, products, supplies and equipment from arms-length third party suppliers;
- the amount paid for any design services included in the Direct Cost, whether provided by Project Co's personnel, consultants, manufacturers or manufacturers' consultants, for hourly paid personnel shall not exceed two times the actual salary received by those personnel (actual salary to be inclusive of all benefits, statutory remittances and holidays), and for salaried personnel, the actual salary per hour shall be calculated by dividing the annual salary (inclusive of all benefits, statutory remittances and holidays) by 2080 hours;
- the amount paid for machinery and equipment rental costs shall not exceed the prevailing competitive commercial rate for which such equipment or machinery can be obtained in Windsor, Ontario; and
- the Direct Cost shall not include any cost incurred due to the failure on the part of Project Co to exercise reasonable care and diligence in its attention to the prosecution of that part of the Project Operations.
APPENDIX B
APPLICABLE MARGINS
| Party |
Total Overhead and Profit Margin (as % of Direct Cost) |
|
For projects under $[REDACTED] |
For projects between $[REDACTED] and $[REDACTED] |
For projects over $[REDACTED] |
| Project Co (Own Work) |
[REDACTED]% |
[REDACTED]% |
[REDACTED]% |
|
|
|
|
| Construction Contractor (Own Work) |
[REDACTED]% |
[REDACTED]% |
[REDACTED]% |
|
|
|
|
| Construction Contractor (Subcontracted Work) |
[REDACTED]% |
[REDACTED]% |
[REDACTED]% |
|
|
|
|
| OM&R Provider (Own Work) |
[REDACTED]% |
[REDACTED]% |
[REDACTED]% |
|
|
|
|
| OM&R Provider (Subcontracted Work) |
[REDACTED]% |
[REDACTED]% |
[REDACTED]% |